问题

某项目最初的网络图如图7-4所示,为了压缩进度,项目经理根据实际情况使用了快速跟进的方法:在任务A已经开始一天后开始实施任务C,从而使任务C与任务A并行3天。这种做法将使项目(13)。

A.完工日期不变

B.提前4天完成

C.提前3天完成

D.提前2天完成

参考答案
正确答案:D
解析:根据项目网络图,其关键路径为ACF,项目工期为20天。使用快速跟进的方法压缩进度后,该项目的关键路径改为BDG,项目的工期为18天。因此,项目提前2天完成。
您可能感兴趣的试题
  • The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

    A.Manage quality

    B.Quality audit

    C.Quality metrics

    D.Quality improvement

  • Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

    A.expert judgment

    B.analogous estimating

    C.requiremen tstraceability matrix

    D.three-point estimating

  • Is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion ?of the network().

    A.Cloud service

    B.Blockchain

    C.Internet of things

    D.Artificial intellingence

  • Is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cognittive computing) or replacing peopleon execution ofnonroutine tasks().

    A.Cloud service

    B.Blockchain

    C.Internet of things

    D.Artificial intellingence