项目进度网络图是(2)。

A.活动定义的结果和活动历时估算的输入

B.活动排序的结果和进度计划编制的输入

C.活动计划编制的结果和进度计划编制的输入

D.活动排序的结果和活动历时估算的输入

参考答案
正确答案:B
解析:项目进度控制的过程大致为活动定义、活动排序、活动资源估算、活动历时估算、进度计划的制定、进度控制。在项目管理中,首先通过对项目活动进行排序,得到项目的进度网络图。再根据项目进度网络图找到项目的关键路径,从而制订项目的进度计划。由此可见,项目进度网络图是活动排序的结果和进度计划编制的输入。
您可能感兴趣的试题
  • The process of translating the qualitymangement plan into executable quality activities that incorporate theorganization's quality policies into the project.

    A.Manage quality

    B.Quality audit

    C.Quality metrics

    D.Quality improvement

  • Estimate activity durations is the processof estimating the number of work periods to complete indivities with estimatedresources . the tools and technques is not including().

    A.expert judgment

    B.analogous estimating

    C.requiremen tstraceability matrix

    D.three-point estimating

  • Is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion ?of the network().

    A.Cloud service

    B.Blockchain

    C.Internet of things

    D.Artificial intellingence

  • Is the technology that appears to emulate human performancetypicaliy by learning,coming to its own conclusions, appearing to understandcomplex content, engaging in natural dialogs with people, enhancing humancognittive performance (also known as cognittive computing) or replacing peopleon execution ofnonroutine tasks().

    A.Cloud service

    B.Blockchain

    C.Internet of things

    D.Artificial intellingence